Arrowhead Union High School Stadium | Hartland, WI

OWNER IN CHARGE

Arrowhead Union High School Stadium 1
Chad Bathke
Chief Operating Officer
PROJECT DETAILS
  • Cost: $2,437,335
  • Stadium and bleacher upgrades
  • Removal of existing home side bleachers and new high-rise home bleachers with a capacity of 3,561 seats
  • Enclosed storage
  • New stadium lighting
  • New stadium sound system
  • New ticket booths and north entrance paving
  • New site fencing
  • New two-tier press box with suites and elevator access
  • Associated sitework and new entrance sign
EXCEPTIONAL RESULTS

Our preconstruction process included numerous budget reviews and updates along with careful value analysis to ensure the final project budget matched the projected fundraising efforts. The ongoing construction duration was estimated at 17 weeks. VJS began construction on June 1 with a construction timeline eight weeks less than originally scheduled. Through extensive coordination and collaboration with the architect and subcontractors, VJS was able to provide the district with a flexible and adaptable approach that included drawing upon our extensive resources and depth of manpower to meet the aggressive schedule without sacrificing quality.

OWNER IN CHARGE

Chad Bathke
Chief Operating Officer